ENGINEERING PROJECTS

For more information on Engineering Projects:
WDM Engineering Services Department, City Hall
4200 Mills Civic Parkway, Suite 2E
P.O. Box 65320
West Des Moines, Iowa 50265
Phone: 515-222-3475
Engineering Services YouTube Channel - Drone videos of construction projects
Project Information Updated
South 60th Street Improvements phase I & II

Estimated Start:  June 2016

Estimated Completion:  December 2017

Contractor:  Concrete Technologies

 

Project Overview:  Reconstruction of South 60th Street from Grand Avenue to Mills Civic Parkway.  

 

Project Status:  South 60th Street is open between Mills Civic Parkway and Grand Avenue.

The contractor will be working on Phase I punch list items and will be finishing up some minor grading on Phase II the remainder of this construction season.

 

Click here for a vicinity/road closure map.

Click here for a drone flyover.

11/28/17

South 88th Street Improvements

Estimated Start:  Spring 2016

Estimated Completion:  December 2017

Contractor:  Hawkeye Paving

 

Project Overview:  The South 88th Street reconstruction project will include grading, utilities, and paving the roadway.

 

Project Status:  The Century Link structures were recently moved and the contractor is finishing the remaining section of pavement.

 

Click here for a vicinity map.

Click here for a drone flyover.

11/28/17
Stagecoach drive extension over sugar creek

Estimated Start:  April 2016

Estimated Completion: October 2017

Contractor:  United Contractors

 

Project Overview:  This projects consists of building the bridge on Stagecoach Drive over Sugar Creek.  The size of the bridge is 135’x30’.  The bridge is to be completed by September 30, 2017.

 

Project Status:  The contractor is nearly complete with the monument signs next to the bridge and will complete the project by early December.

 

Click here for a vicinity map.

11/28/17
2017 PCC Patching and Medians program Estimated Start:  August 2017

Estimated Completion:  11/22/2017

Contractor:  Concrete Company

 

Project Overview:  Portland Cement Concrete (PCC) Patching at various locations including approximately 3,381 SY of reinforced 7” PCC full depth patching, 120 SY of reinforced 8” PCC full depth patching, 802 SY of reinforced 9” PCC full depth patching, 215 SY of reinforced 8” PCC full depth patching (IA DOT 5 Hr. PCC Mix), 530 SY of reinforced 9” PCC full depth patching (IA DOT 5 Hr. PCC Mix), 47 SY of reinforced 10” PCC full depth patching (IA DOT 5 Hr. PCC Mix), PCC curb and gutter replacement, intake reconstruction, manhole adjustments, drives, sidewalks, traffic control, traffic loops, and other miscellaneous work to complete the project.

 

Project Status:  The contractor recently completed the project.

 

Mills Civic Detour Map

Click here for a vicinity map.

11/28/17
2017 parking lot repairs Estimated Start:  Spring 2017

Estimated Completion:  09/01/2017

Contractor:  JDA

 

Project Overview: 

Portland Cement Concrete (PCC) Patching of parking lots at Fire Stations 17, 18, and 19 in West Des Moines including approximately 2,868 SY of reinforced 8” PCC full depth patching, 130 SY of double reinforced 10” PCC full depth patching, 185 SY of reinforced 8” PCC full depth patching (IA DOT 5 Hr. PCC Mix), PCC curb and gutter, subdrain installation, sidewalks, traffic control and other miscellaneous work to complete the project.

 

Project Status:  They have completed Station #17, Station #19 and Station #18 repairs.  They have been working on punch list items and restoration.

 

Click here for a vicinity map.

11/28/17
SW 60th Street, SE 50th Street and SE/SW Adams Street
Estimated Start:  July 2017

Estimated Completion:  Fall 2017

Contractor:  Alliance Construction

 

Project Overview:  Construct SW 60th Street, SE 50th Street and SE/SW Adams Street including all materials, labor and equipment necessary for installation of approximately 6,800 CY of grading, 4800 SY of 8 in. PCC paving, 18400 SY of 8 in. reinforced PCC paving, 1060 SY of 9 in. reinforced PCC paving, 400 SY of bridge approach pavement, surface restoration, erosion control, pavement markings, traffic control and miscellaneous related work and appurtenances.  

 

Project Status:  The contractor is working on punch list items.

 

Click here for a vicinity map.

11/28/17
South Grand Prairie Parkway
Estimated Start:  July 2017

Estimated Completion:  Fall 2018

Contractor:  SM Hentges & Sons

 

Project Overview:  Construct S. Grand Prairie Parkway from SW Madison Avenue to Raccoon River Drive including all materials, labor and equipment necessary for installation of approximately: 2,400 LF of sanitary sewer, 6,190 LF of storm sewer with 37 structures, 6,925 LF of   24-inch water main including an encased river crossing, 462,170 CY of grading, 23,670 SY of PCC pavement and bridge approach, a 538-ft x 30-ft pretensioned prestressed concrete beam bridge with a 12-ft trail, 55 ACRES of surface restoration, erosion control including 9,940 TON of riprap, pavement markings, traffic control and miscellaneous related work and appurtenances.

 

Project Status:  The contractor has completed mass grading between the Raccoon River and Raccoon River Drive for 2017.  They started bridge construction and sanitary & water main river crossing the week of October 16th.  The bridge work is anticipated to be complete by March 2018.

 

Click here for a vicinity map.

Click here for a drone flyover.

11/28/17
Ashworth Road Reconstruction
Estimated Start:  August 2017

Estimated Completion:  Fall 2018

Contractor:  Alliance Construction

 

Project Overview:  Construction of the Ashworth Road from Jordan Creek Parkway to 81st Street including 6,000 CY of Topsoil, 13,800 CY of Excavation, 7,000 CY of Below Grade Excavation (Core Out), 19,750 SY of Subgrade Preparation.  2,864 LF of Storm Sewer, 29 Storm Sewer Intakes and 4 Storm Sewer Manholes.  2,713 LF of Subdrain, Subdrain Outlets and Connections.  204 LF of Water Main and Fittings.  23 LF of Sanitary Sewer and 1 sanitary sewer manhole.  800 SY of 6 inch Non-Reinforced PCC, 920 SY of 6 inch Reinforced PCC Pavement, 218 SY of 7 inch Reinforced PCC Pavement, 17,460 SY of 9.5 inch Reinforced PCC Pavement, 2,496 SY of PCC Driveway, 2,427 SY of PCC Shared Use Path, and pavement, sidewalk and driveway removals.  And other miscellaneous work including Clearing and Grubbing, Traffic Control, Construction Survey, Erosion Control, Pavement Markings, Seeding, Fixture Adjustments and other Miscellaneous Removals.

 

Project Status:  Ashworth Road is now open from Jordan Creek Parkway to 81st Street.  All sanitary and storm sewer work was completed this fall.  Grading and paving will begin when weather allows in the spring 2018.

Ashworth Road Phase I Jordan Creek Parkway to 81st Street will be closed from spring to late summer.  Phase II will be closed from 81st Street to 88th Street from spring to winter in 2018.

 

Click here for a vicinity map.

11/28/17
COACHLIGHT DRIVE (s 81ST sTREET TO sOUTH jORDAN cREEK pARKWAY) Estimated Start:  Fall 2017

Estimated Completion:  Summer 2018

Contractor:  Absolute Concrete

 

Project Overview:  Construction of Coachlight Drive and S 77th St, including all materials, labor, and equipment necessary for the project including the approximate quantities: 12,968 SY of PCC paving, 20,150 CY of excavation, 4929 LF of storm sewer, 2941 LF of sanitary sewer, and 3718 LF of water main. 

 

Project Status:  The contractor is grading the site, installing watermain and storm sewer.

 

Click here for a vicinity map.

11/28/17
cHANNEL rEPAIR pROGRAM Estimated Start:  August 2017

Estimated Completion:  Winter 2017

Contractor:  McGregor Corporation

 

Project Overview:  Sanitary sewer concrete encasements, excavation, grading, rip rap placement, restoration of approximately 760 feet of stream bank, native seeding, live stake plantings, erosion control and access restoration at three locations along Jordan Creek to protect the City’s sanitary sewer infrastructure.

 

Project Status:  The contractor is working on the repairs adjacent to 68th Street and along EP True Parkway.  The trail has been reopened.

 

Click here for a vicinity map.

11/28/17
98TH sTREET / uNIVERSITY aVENUE tRAFFIC sIGNAL Estimated Start:  August 2017

Estimated Completion:  Winter 2017

Contractor:  Jasper Construction

 

Project Overview:  Construction of traffic signals and pedestrian ramps including all labor, materials and equipment necessary to remove existing sidewalks, remove existing roadway median, erosion control, and miscellaneous associated work, including cleanup.

 

Project Status:  The contractor is working on the signal portion.

 

Click here for a vicinity map.

11/28/17

 

PARKS & RECREATION PROJECTS

For more information on Parks & Recreation Projects:
WDM Parks & Recreation Department, City Hall
4200 Mills Civic Parkway, Suite 1B
P.O. Box 65320
West Des Moines, Iowa 50265
Phone: 515-222-3444
Email:
ParkRec@wdm.iowa.gov
 
 Project  Information Updated
Holiday Park Baseball Improvements - Phase 4B and 5

Estimated Start:  June 2017
Estimated Completion:  October 2017
Contractor:  Iowa Athletic Field Construction
Project Overview:  Improvements to fields 7 and 8 (phase 4B) and fields 9 and 10 (phase 5). Improvements will include renovation of the existing ballfields including new infield material, sod, irrigation and dugouts. Other site improvements will include new pedestrian walkways, field lighting, and storm water improvements.

 

Project Status: Contractor has substantially completed the project. Remaining punch list items will be completed over the next several weeks.
Click here for a vicinity map.

 11/3/17   
Woodland Hills Park Site Development

Estimated Start:  Summer 2016
Estimated Completion:  Spring 2017
Contractor:  Joiner Construction, Inc.
Project Overview:  Development of Woodland Hills Park located at 1230 S. 95th Street. Improvements include construction of a 2-5 and 5-12 yr-old playground; shelter; restroom; parking lot; and concrete walks. Water quality measures will also be incorporated including permeable pavers, bioretention cells, and soil restoration.

 

Project Status: Contractor has completed the project and the park is officially open. 
Click here for a vicinity map.

Click here for park overview

 8/11/17
Valley View Park Tennis Courts

Estimated Start:  2017
Estimated Completion:  Fall 2017
Contractor:  Grimes Asphalt and Paving
Project Overview:  Construction of a pair of lighted asphalt tennis courts.

 

Project Status: Contractor has substantially completed the project. Remaining punch list items will be completed over the next several weeks.
Click here for a vicinity map.

  11/3/17
Fairmeadows Park Playground Replacement 

Estimated Start:  Summer 2017
Estimated Completion:  Fall 2017
Contractor:  Caliber Concrete
Project Overview:  Last Fall a City Engineering project to replace a storm sewer pipe under Locust Street directly impact the park including removal of the playground equipment, volleyball court, portions of sidewalk, misc tree removals, and stream channel reconstruction. This Spring, a separate Parks project will be contracted to restore the park including new playground equipment, sidewalks, and site restoration. During construction the park will remain closed to the public. 

 

Project Status: Contractor has substantially completed the project. Remaining punch list items will be completed over the next several weeks.

Click here for Illustrated Plan of Improvements

  11/3/17
39TH STREET PARKING LOT

Estimated Start:  Summer 2017
Estimated Completion:  Fall 2017
Contractor:  Caliber Concrete
Project Overview:  Construction of a 45-stall parking lot with two access drives off of 39th Street. The parking lot will serve as a trail head for Jordan Creek Trail as well as serve as overflow parking for the Rugby Club located across the street. Project includes utility adjustments, site grading, storm water improvements, concrete paving, erosion control and site restoration.

 

Project Status: Contractor has completed paving of the parking lot and trail connection. Remaining items including parking lot striping and site restoration will be completed in the several weeks.
Click here for a vicinity map.

  11/3/17
MIsc. Trail PROJECTS

Estimated Start:  2016
Estimated Completion:  Multiple
Contractor:  Multiple
Project Overview:  The following street projects include segments of multi-use trail that will be constructed as part of the overall street improvement project: SE Soteria Ave; South 50th St Reconstruction; South 60th St Improvements; Grand Prairie Pkwy; Stagecoach Dr Extension.

 

Project Status: Please refer to the corresponding street project under Engineering Projects for project updates.
Click here for a vicinity map.

 12/02/16
2017 Concrete Trail Renovation Project Estimated Start:   2017
Estimated Completion:  Summer 2017
Contractor:  Tricrete Construction
Project Overview:  Removal and replacement of damaged concrete panels on existing 10’ wide multi-use trails located generally around Wells Fargo Campus.

 

Project Status: Contractor has completed the project including site restoration.
Click here for a vicinity map.

11/3/17
RACCOON RIVER PARK PORTABLE TOILET ENCLOSURES & PICNIC SHELTER Estimated Start:   Summer 2017
Estimated Completion:  Fall 2017
Contractor:  Minturn Inc.
Project Overview:  Construction of enclosures to screen (3) portable toilets located throughout Raccoon River Park. In addition, project also includes installation of a small picnic shelter near the Fishing Pier. Other associated items include concrete slabs, sidewalks, footings, and site restoration.

 

Project Status: Contractor is finalizing submittals related to screen enclosures. Concrete work including footings and flat work is scheduled to take place the week of November 13.
Click here for a vicinity map.

11/3/17
S. 19TH STREET TRAIL & SIDEWALK Estimated Start:   Spring 2017
Estimated Completion:  Summer 2017
Contractor:  Concrete Professionals of Iowa
Project Overview:  Removal of the older segment of asphalt trail along S. 19th Street and replacement with a standard 4’ wide concrete sidewalk.  Work includes traffic control, concrete & asphalt removals, drive & curb replacements, installation of concrete sidewalk & small section of trail, site restoration, and other associated work.

 

Project Status: Contractor has completed the project including site restoration.
Click here for a vicinity map.

 11/3/17
RACCOON RIVER PARK SOFTBALL IRRIGATION MODIFICATIONS Estimated Start:   Summer 2017
Estimated Completion:  Fall 2017
Contractor:  Landscape Unlimited LLC (Lincoln, NE)
Project Overview:  Construction of a pump station to pull water from Blue Heron Lake to supply the irrigation needs for the Raccoon River Park Softball Complex.  This project includes the installation of a pump station, associated piping, valves, inlet box screen, electrical control panel, and 6” HDPE piping. The project also includes plumbing modifications in the existing softball maintenance building to convert the irrigation system from potable water to water pumped from the lake.

 

Project Status: Contractor has completed the project.
Click here for a vicinity map.

 11/10/17
Holiday & VALLEY VIEW AQUATIC STAIR STRUCTURE REFURBISHMENT Estimated Start:   Fall 2017
Estimated Completion:  Fall 2017
Contractor:  Elevation Coating LLC (St Cloud, MN)
Project Overview:  Refurbishment of water slide structure at Holiday and Valley View Park. Work includes removing existing finish, replacement of corroded components, and re-coating of structure.

 

Project Status: Contractor is approximately 90 percent complete. Remaining work includes reattaching stair structure and site cleanup.
Click here for a vicinity map.

 11/10/17
HOLIDAY AQUATIC PLAY STRUCTURE REFURBISHMENT Estimated Start:   Fall 2017
Estimated Completion:  Spring 2018
Contractor:  Fischer Bros. LLC (Chippewa Falls, WI)
Project Overview:  Refurbishment of play structure at Holiday Aquatic Center. Work includes removing existing finish, replacement of corroded components, and re-coating of entire structure.

 

Project Status: Contractor will be onsite week of November 13 to begin disassembly of structure. Work is anticipated to be completed prior to pool opening in 2018.  
Click here for a vicinity map.

  11/10/17
RACCOON RIVER PARK ENTRANCE TRAIL Estimated Start:   Fall 2017
Estimated Completion:  Fall 2017
Contractor:  City of West Des Moines
Project Overview:  Construction of multi-use trail across railroad at entrance to Raccoon River Park.

 

Project Status: City staff has completed installation of concrete trail crossing. Remaining work includes removing vegetation along railroad tracks to improve visibility. Work is anticipated to be complete week of November 13.
Click here for a vicinity map.

  11/10/17
2017 Asphalt TRAIL RENOVATION - KNOLLS GREENWAY TRAIL Estimated Start:   Spring 2018
Estimated Completion:  Spring 2018
Contractor:  Grimes Asphalt
Project Overview:  Renovation of a ¼ mile section of asphalt trail located in Knolls Greenway between Aspen Drive and Ashworth Road. Project will include full depth on-site recycling of the existing trail to act as base for a new 3" HMA overlay. Other associated item include pavement removals, new sidewalk and pedestrian ramps with detectable warning panels, traffic control, and site restoration (seeding).

 

Project Status: Contractor is scheduled to begin work in early spring 2018.
Click here for a vicinity map.

 11/10/17