 Overall Map of 2010 Proposed Street Maintenance Construction

 

Grand Avenue Phase II

Est. Start: Spring 2009

Est. Completion: Winter 2009

Est. Cost: $3,987,415.97

Contractor: Corell Contractor

Description: This is a reconstruction project that will provide public improvements north of the intersection of Grand Avenue and Fuller Road to approximately Delavan Drive.

Project Status:  The road is open to through traffic.

Final restoration and punch list items will be completed in the Spring of 2010.

Click here for a vicinity map.

Grand Avenue Phase III

Est. Start: Spring 2010

Est. Completion: December 2010

Est. Cost: $3,592,912

Contractor: Corell Contractor

Description: This is a reconstruction project that will provide public improvements south of the intersection of Grand Avenue/Fuller Road to Raccoon River Park entrance.

Project Status:  The project will start in the Spring of 2010 as weather permits.

Click here for a vicinity map.

2009 PCC Patching Program - Phase I

Est. Start: June 11, 2009

Est. Completion: Spring 2010

Est. Cost: $538,884.70

Contractor: Corell Contractor

Description: This is a maintenance project that will replace 6,270 square yards of paving at various locations.

Project Status: The contractor has suspended work due to winter weather.  The contractor is approximately 98% complete with the project.

Click here for a vicinity map.

2009 PCC Patching Program - Phase II

Est. Start: August 3, 2009

Est. Completion: Spring 2010

Est. Cost: $405,733.75

Contractor: TK Concrete

Description: This is a maintenance project that will replace 5,808 square yards of paving at various locations.

Project Status: The remaining subdrain work along 52nd Place will be delayed until spring as well as all other clean up and restoration.  The contractor is approximately 95% complete with the project.

Southwest Connector Tree Clearing Project

Est. Start: February 2, 2010

Est. Completion: March 31, 2010

Est. Cost: $65,075.00

Contractor: TK Concrete

Description: This is a tree clearing project for the Southwest Connector road construction project that will start in the spring of 2010.

Project Status: The contractor has started removing trees within the project.

Click here for a vicinity map.

 